  • 24 teams spent 16 hours in the field and started power supply in 123 villages of Santalpur-Radhanpur during the week.

In both Radhanpur and Santalpur talukas of Patan, a total of 24 teams were deployed to restore electricity supply to 123 villages due to storm Biparjoy, which caused blackout due to broken power poles and wires. After seven days of hard work of more than 16 hours a day, electricity supply has finally been restored in all the villages and about 50,000 houses have been lit.

Executive Engineer Rakesh Vasava and Warahi Sub Division Deputy Engineer Pragnesh Kharadi both expressed their views to Divyabhaskar about the day and night operation amid dangerous conditions.

The team reached the spot by removing the trees on the road
Executive Engineer Rakesh Vasava said that the head office officials along with 96 employees have set up a camp in Radhanpur and worked in the field to start power supply in both the talukas with 200 power poles and 170 broken wires.

They used to give foot packages in the afternoon. Teams would reach the villages from early morning, to reach the place, they would remove the trees lying in the middle of the road by themselves and reach the location.
Worked till midnight and completed a month’s work in a week
Varahi Deputy Engineer Prajnesh Kharadi said that first 11 Kv lines were repaired and the bent bridges were broken. If the bent bridges were broken, the new ones were started by supplying power to the transformer and starting the electricity in the villages. The teams stayed in the field till twelve o’clock in the night.

When they did not get food in the afternoon, they used to fill their stomachs with what they got in the food packets. If the repairing work of electricity pole and wire breakage in the villages is to be done without the help of the outside team as usual, it may take a month, but it has been completed in a week to remove the problems of the people.

.

gnews24x7.com

Recent Posts

Why Every Business Needs a Website in 2026

In today’s digital-first world, a business without a website is like a shop without a…

1 month ago

Netflix Rom-Com Based on Bestselling Novel

Netflix Rom-Com Based on Bestselling Novel Debuts With 88% Rotten Tomatoes Score Netflix’s new romantic…

1 month ago

General Hospital Fans Want Drew’s Storyline to End After Shooter Reveal

For months, General Hospital fans have been urging the writers to finally wrap up the…

1 month ago

The Odyssey’s Matt Damon Reveals How Much Weight He Lost for Odysseus

Matt Damon on His Dramatic Weight Loss for The Odyssey Matt Damon has never been…

1 month ago

Trump withdraws US from dozens of international and UN entities

Trump Announces U.S. Withdrawal from Dozens of UN and International Bodies, Citing National Interests U.S.…

1 month ago

Taylor Swift Reveals Elizabeth Taylor’s Estate’s Reaction to The Life of a Showgirl Song

Taylor Swift’s latest album, The Life of a Showgirl, includes a track inspired by the…

4 months ago